Bikeway Route Phase 2 (7th Ave. E. to Main Ave)

Project Related Road Closures

  • 7th Ave. E. will close at Drain 45 (between 3rd St. E. 5th St. Ct. E.) from approx. June 20 - June 30
  • 3rd Ave E. will close down to one lane at 4th St. E. from approx. June 20 - June 30.  Traffic will be able to drive in both directions but it will be congested
  • Saw cutting underway that may cause loud noises during the day and into evening hours. 

Project Information

City of West Fargo identified a need for a north/south bikeway route that adds connectivity between 13th Avenue E. and Main Avenue. This route will run along drain 45.

Phase 1 of this project was completed from 13th Ave E. to 7th Ave E. in 2021. and Phase 2 from 7th Ave E to Main Ave. will be complete in 2022. 

Project Cost

  • Estimated project cost: $632,000

Project Status

  • Phase 2 path construction underway - work being done at intersections. 
  • Phase 1 Complete.
Map - Square